Apartment Finishing BOQ Template (Free Excel & PDF)

By AFAQ Development team · Updated

AFAQ site team checking the stone facade of a residential building in Badr City from the street
From an AFAQ site in Badr City

An apartment finishing BOQ (bill of quantities, moqaysa in Egypt) is a table of every item of work, with its unit, quantity, material and price. Our free template lists the items for a typical apartment, from demolition and rough-in to painting, fittings and handover, without prices, so you can fill in quantities and ask several companies to price exactly the same items.

Download: BOQ template, Excel · BOQ template, PDF

The full item list is also at the end of this article under “Full list of BOQ items”.

What is a finishing BOQ?

A BOQ is the written list of all the work to be done, each item with a description, unit, quantity, unit rate and total. The contract, payment stages and final account are all built on it. A quantity take-off is the quantities alone, without prices; a quotation may be a single lump sum. A good quotation is a priced BOQ.

What is in the template?

Each row has: item code, section, description, unit, measurement rule, specification or material, quantity, unit rate, total and notes. In the download, the first five columns are filled in; the rest are left for you, your engineer and the company.

Why ask for an itemised BOQ instead of a price per metre?

A flat rate per square metre does not tell you what is included; a BOQ does. A “super lux per metre” price may exclude gypsum ceilings, sanitaryware or debris removal, which then reappear as extras. An itemised BOQ gives you a fair comparison between companies, a basis for stage payments, and a clear final account: actual quantity × agreed unit rate.

What units are used in a finishing BOQ?

Finishing BOQ items are measured in seven units: square metres, linear metres, cubic metres, number, point, set or lump sum, with debris sometimes priced per load.

Unit Meaning Examples
m² Area Plaster, paint, porcelain, gypsum board, waterproofing, half-brick walls
lm (linear metre) Length Skirting, cove lighting, curtain pelmets, sills, kitchen units
m³ Volume Bathroom fill, full-brick walls, sometimes debris
No. Each Doors, sanitaryware, mixers, light fittings
Point One complete electrical or plumbing outlet Light point, socket point, water point
Set A group of pieces priced together Door ironmongery, bathroom accessories
Lump sum Fixed price for a defined job Final clean, pressure test, earthing

A lump-sum item must state exactly what it covers, or it becomes a source of dispute.

How do you measure the quantities yourself?

  1. Print the floor plan and mark each room’s length, width and height.
  2. Floors: length × width per room; bathrooms and kitchen separately.
  3. Walls (plaster and paint): room perimeter × height, minus openings according to the deduction rule you agree. Walls that will be tiled count for plaster only, not for paint.
  4. Ceilings: roughly the floor area of each room.
  5. Bathroom wall tiles: perimeter × tiling height, minus the door.
  6. Skirting: perimeter minus door widths.
  7. Electrical and plumbing: count points from the layout drawing, room by room.
  8. Doors, windows, sanitaryware: count them, with sizes.
  9. Wastage: agree whether it is included in the rate or charged separately.

The key question is the opening-deduction rule: are windows and doors deducted from plaster and paint areas, all of them or only those above a certain size? Put the rule in the contract; it affects every wall item.

How do you compare quotes using the BOQ?

Send the same BOQ, with the same items and specifications, to every company, and ask them to price each item without changing the description. Then any difference is a real price difference, not a different material or a missing item. Fix specifications first (brand and size, or a provisional sum for items not yet chosen), ask for unit rates, compare line by line, and question any item priced far below the others or marked “by client”. Then ask each company about the contract type and which engineer will follow the work, and get the answers in writing.

Which items are commonly left out?

Debris removal; carrying materials up to the floor if there is no lift you are allowed to use; protecting floors and windows during work; pipe pressure tests and bathroom flood tests; earthing and the feed from the meter to the panel; skirting, door thresholds and window sills; curtain pelmets and access panels in ceilings; corner beads; balcony finishes; bathroom accessories; and the final clean.

Does the BOQ change for bare-brick versus semi-finished units?

Yes. A bare-brick unit needs every item from rough-in and plaster; a semi-finished unit drops what the developer delivered and adds repair items for anything substandard. Check what you actually received with our semi-finished handover checklist, see what semi-finished means, and follow the finishing stages in order.

How does AFAQ write a finishing BOQ?

At AFAQ Development, every item is written into the BOQ with its material before work starts, and the work follows a fixed sequence under an engineer’s supervision. If you want AFAQ to price these items, the price is set after a site visit, because it depends on the area, finishing level, materials and the unit’s current condition, and it comes to you as a BOQ priced line by line, either with materials (turnkey) or labour-only, as you choose. See apartment finishing, send us your apartment’s size and condition on WhatsApp (and your BOQ, if you already have one), or get in touch.

Full list of BOQ items

Full item list for a typical apartment, no prices. Each item has a fixed code, and the same codes are used in the Excel file. Delete items you do not need.

Code Section Item Unit How the quantity is measured
A01 General Site survey and measurement Lump sum Once per apartment
A02 General Electrical, plumbing and AC layout drawings Lump sum Once per apartment (or per m² of floor area, per contract)
A03 General Protection of existing front door, windows and floors during work Lump sum Whole apartment
A04 General Debris removal off site Load or m³ Actual loads or volume
A05 General Final clean before handover Lump sum Whole apartment
A06 General Carrying materials up to the floor (if no usable lift) Lump sum Whole apartment, by floor
B01 Demolition & masonry Demolish brick walls m² Wall length × height (or m³ including thickness)
B02 Demolition & masonry Break out old floor tiles m² Floor area broken out
B03 Demolition & masonry Hack off old plaster m² Wall area hacked off
B04 Demolition & masonry Remove old doors and windows No. Number of pieces
B05 Demolition & masonry Half-brick walls m² Length × height minus openings
B06 Demolition & masonry Full-brick walls m³ Length × height × thickness minus openings
B07 Demolition & masonry Lintels over new openings No. Number of openings
C01 Electrical Feed cable from meter to distribution board lm Actual route length
C02 Electrical Distribution board with breakers No. Number of boards, each sized by number of circuits
C03 Electrical Lighting point (conduit, cable, box) Point Count from layout drawing
C04 Electrical Standard socket point Point Count from drawing
C05 Electrical Power socket point (AC, heater, oven) Point Number of heavy appliances
C06 Electrical Telephone or data point Point Count
C07 Electrical Satellite or TV point Point Count
C08 Electrical Doorbell or intercom point Point Count
C09 Electrical Spare empty conduits (data, cameras) lm Conduit length
C10 Electrical Earthing Lump sum Whole apartment
C11 Electrical Supply and fix switch and socket plates No. Number of plates from the layout drawing (one plate can serve several points)
C12 Electrical Downlights and spotlights No. Count from lighting plan
C13 Electrical Concealed LED lighting (strip or profile) lm Strip length
C14 Electrical Install chandeliers and special fittings No. Count
D01 Plumbing Bathroom water supply rough-in (hot and cold) Point Water points per bathroom (or lump sum per bathroom)
D02 Plumbing Bathroom drainage rough-in Point Drain points (or lump sum per bathroom)
D03 Plumbing Kitchen supply and drainage rough-in Point Count
D04 Plumbing Washing machine point (supply and drain) Point Count
D05 Plumbing Water heater point Point Number of heaters
D06 Plumbing Main supply line from meter or tank lm Route length
D07 Plumbing Main and branch valves No. Count
D08 Plumbing Floor drains No. Count
D09 Plumbing Connection to soil stack No. Number of connections
D10 Plumbing Pipe pressure test Lump sum Whole apartment
E01 AC Copper pipe rough-in lm Route length per unit (or point per unit by capacity)
E02 AC Condensate drain rough-in lm Route length to discharge point
E03 AC Opening and bracket for outdoor unit No. Number of units
E04 AC Install AC units No. Number of units (if not by supplier)
F01 Waterproofing Bathroom floor waterproofing turned up walls m² Floor area + perimeter × upstand height
F02 Waterproofing Kitchen floor waterproofing m² Floor area + upstand
F03 Waterproofing Balcony waterproofing m² Floor area + upstand
F04 Waterproofing Flood test Lump sum Per bathroom or waterproofed area
G01 Plaster Spatterdash (key coat) m² Same as plaster area
G02 Plaster Internal wall plaster with dots and screeds m² Room perimeter × height minus openings per deduction rule
G03 Plaster Ceiling plaster m² Room length × width
G04 Plaster Corner beads on external corners lm Length of corners
G05 Plaster Mesh at brick-to-concrete joints lm Length of joints
G06 Plaster Repair existing plaster (semi-finished units) m² Area needing repair
H01 Floors & walls Bathroom fill m³ Area × depth
H02 Floors & walls Levelling screed, if required m² Floor area
H03 Floors & walls Porcelain, ceramic or marble floors (inside the apartment) m² Net floor area per room
H04 Floors & walls Bathroom wall tiles m² Perimeter × tiling height minus door
H05 Floors & walls Kitchen wall tiles m² Wall length × tiling height
H06 Floors & walls Porcelain or marble skirting lm Perimeter of rooms with porcelain or marble floors, minus door widths
H07 Floors & walls Marble door thresholds lm Width of each door
H08 Floors & walls Marble window sills lm Width of each window
H09 Floors & walls Parquet or HDF with underlay m² Net floor area
H10 Floors & walls Parquet skirting lm Perimeter of rooms with parquet floors, minus door widths
H11 Floors & walls Balcony flooring m² Balcony area
I01 Gypsum board Suspended gypsum board ceiling m² Plan area of suspended ceiling
I02 Gypsum board Cove for concealed lighting lm Cove length
I03 Gypsum board Curtain pelmet lm Window or wall width
I04 Gypsum board Ready-made gypsum cornices lm Room perimeter
I05 Gypsum board Access and AC openings No. Count
I06 Gypsum board Gypsum board partitions or wall linings m² Length × height
J01 Painting Sealer m² Same as painted area (walls and ceilings)
J02 Painting Putty and sanding (number of coats) m² Same as painted area (walls and ceilings)
J03 Painting Wall paint (coats and brand) m² Perimeter × height minus openings per deduction rule, excluding tiled walls
J04 Painting Ceiling paint m² Painted ceiling area, including gypsum board surfaces
J05 Painting Special finishes or wallpaper m² Wall area specified
J06 Painting Metal painting (railings, iron windows and doors) lm / m² lm for railings, m² for iron windows and doors
K01 Doors & windows Apartment front door No. Count, with size
K02 Doors & windows Internal doors with frame and architrave No. Count, with size of each
K03 Doors & windows Handles, hinges and locks Set One set per door
K04 Doors & windows Aluminium windows with glazing (and shutters if required) m² Opening width × height per window
K05 Doors & windows Aluminium balcony doors m² Opening width × height
K06 Doors & windows Insect screens m² Sash area
K07 Doors & windows Balcony railing lm Railing length
L01 Sanitaryware WC (floor or wall-hung) with cistern No. Count
L02 Sanitaryware Washbasin with pedestal or bracket No. Count
L03 Sanitaryware Basin mixer No. Count
L04 Sanitaryware Shower or bath mixer (exposed or concealed) No. Count
L05 Sanitaryware Bathtub, shower tray or enclosure No. Count
L06 Sanitaryware Bidet spray (shattaf) No. Count
L07 Sanitaryware Water heater No. Count
L08 Sanitaryware Bathroom accessories (hooks, roll holder, mirror) Set One set per bathroom
L09 Sanitaryware Kitchen sink and mixer No. Count
M01 Kitchen & joinery Kitchen base units lm Run length
M02 Kitchen & joinery Kitchen wall units lm Run length
M03 Kitchen & joinery Worktop (marble, granite or quartz) lm Worktop length
M04 Kitchen & joinery Built-in wardrobes m² Front width × height
M05 Kitchen & joinery Install cooker hood No. Count
N01 Handover Testing of electrical and plumbing systems Lump sum Whole apartment
N02 Handover Rectification of handover snags Lump sum Per handover record; agree it is included in the item rates and has a deadline

Frequently asked questions

What is the difference between a BOQ and a quotation?

A BOQ details every item with unit, quantity and rate; a quotation can be a single figure. Always ask for a quotation in BOQ form.

Can I prepare my own finishing BOQ?

You can measure most quantities from room sizes using the template, but technical specifications (cable size, waterproofing type, coats of putty) are best reviewed by an engineer.

Does the final price change if actual quantities differ?

In many contracts the final account is actual measured quantities × agreed unit rates. The contract should say so and state the measurement rules.

Does the template include prices?

No. Prices change quickly and depend on the material, so the template gives items, units and measurement rules, and you ask companies to price them. AFAQ also sets its price after a site visit, not as a flat rate per square metre.