Apartment Finishing BOQ Template (Free Excel & PDF)
By AFAQ Development team · Updated

An apartment finishing BOQ (bill of quantities, moqaysa in Egypt) is a table of every item of work, with its unit, quantity, material and price. Our free template lists the items for a typical apartment, from demolition and rough-in to painting, fittings and handover, without prices, so you can fill in quantities and ask several companies to price exactly the same items.
Download: BOQ template, Excel · BOQ template, PDF
The full item list is also at the end of this article under “Full list of BOQ items”.
What is a finishing BOQ?
A BOQ is the written list of all the work to be done, each item with a description, unit, quantity, unit rate and total. The contract, payment stages and final account are all built on it. A quantity take-off is the quantities alone, without prices; a quotation may be a single lump sum. A good quotation is a priced BOQ.
What is in the template?
Each row has: item code, section, description, unit, measurement rule, specification or material, quantity, unit rate, total and notes. In the download, the first five columns are filled in; the rest are left for you, your engineer and the company.
Why ask for an itemised BOQ instead of a price per metre?
A flat rate per square metre does not tell you what is included; a BOQ does. A “super lux per metre” price may exclude gypsum ceilings, sanitaryware or debris removal, which then reappear as extras. An itemised BOQ gives you a fair comparison between companies, a basis for stage payments, and a clear final account: actual quantity × agreed unit rate.
What units are used in a finishing BOQ?
Finishing BOQ items are measured in seven units: square metres, linear metres, cubic metres, number, point, set or lump sum, with debris sometimes priced per load.
| Unit | Meaning | Examples |
|---|---|---|
| m² | Area | Plaster, paint, porcelain, gypsum board, waterproofing, half-brick walls |
| lm (linear metre) | Length | Skirting, cove lighting, curtain pelmets, sills, kitchen units |
| m³ | Volume | Bathroom fill, full-brick walls, sometimes debris |
| No. | Each | Doors, sanitaryware, mixers, light fittings |
| Point | One complete electrical or plumbing outlet | Light point, socket point, water point |
| Set | A group of pieces priced together | Door ironmongery, bathroom accessories |
| Lump sum | Fixed price for a defined job | Final clean, pressure test, earthing |
A lump-sum item must state exactly what it covers, or it becomes a source of dispute.
How do you measure the quantities yourself?
- Print the floor plan and mark each room’s length, width and height.
- Floors: length × width per room; bathrooms and kitchen separately.
- Walls (plaster and paint): room perimeter × height, minus openings according to the deduction rule you agree. Walls that will be tiled count for plaster only, not for paint.
- Ceilings: roughly the floor area of each room.
- Bathroom wall tiles: perimeter × tiling height, minus the door.
- Skirting: perimeter minus door widths.
- Electrical and plumbing: count points from the layout drawing, room by room.
- Doors, windows, sanitaryware: count them, with sizes.
- Wastage: agree whether it is included in the rate or charged separately.
The key question is the opening-deduction rule: are windows and doors deducted from plaster and paint areas, all of them or only those above a certain size? Put the rule in the contract; it affects every wall item.
How do you compare quotes using the BOQ?
Send the same BOQ, with the same items and specifications, to every company, and ask them to price each item without changing the description. Then any difference is a real price difference, not a different material or a missing item. Fix specifications first (brand and size, or a provisional sum for items not yet chosen), ask for unit rates, compare line by line, and question any item priced far below the others or marked “by client”. Then ask each company about the contract type and which engineer will follow the work, and get the answers in writing.
Which items are commonly left out?
Debris removal; carrying materials up to the floor if there is no lift you are allowed to use; protecting floors and windows during work; pipe pressure tests and bathroom flood tests; earthing and the feed from the meter to the panel; skirting, door thresholds and window sills; curtain pelmets and access panels in ceilings; corner beads; balcony finishes; bathroom accessories; and the final clean.
Does the BOQ change for bare-brick versus semi-finished units?
Yes. A bare-brick unit needs every item from rough-in and plaster; a semi-finished unit drops what the developer delivered and adds repair items for anything substandard. Check what you actually received with our semi-finished handover checklist, see what semi-finished means, and follow the finishing stages in order.
How does AFAQ write a finishing BOQ?
At AFAQ Development, every item is written into the BOQ with its material before work starts, and the work follows a fixed sequence under an engineer’s supervision. If you want AFAQ to price these items, the price is set after a site visit, because it depends on the area, finishing level, materials and the unit’s current condition, and it comes to you as a BOQ priced line by line, either with materials (turnkey) or labour-only, as you choose. See apartment finishing, send us your apartment’s size and condition on WhatsApp (and your BOQ, if you already have one), or get in touch.
Full list of BOQ items
Full item list for a typical apartment, no prices. Each item has a fixed code, and the same codes are used in the Excel file. Delete items you do not need.
| Code | Section | Item | Unit | How the quantity is measured |
|---|---|---|---|---|
| A01 | General | Site survey and measurement | Lump sum | Once per apartment |
| A02 | General | Electrical, plumbing and AC layout drawings | Lump sum | Once per apartment (or per m² of floor area, per contract) |
| A03 | General | Protection of existing front door, windows and floors during work | Lump sum | Whole apartment |
| A04 | General | Debris removal off site | Load or m³ | Actual loads or volume |
| A05 | General | Final clean before handover | Lump sum | Whole apartment |
| A06 | General | Carrying materials up to the floor (if no usable lift) | Lump sum | Whole apartment, by floor |
| B01 | Demolition & masonry | Demolish brick walls | m² | Wall length × height (or m³ including thickness) |
| B02 | Demolition & masonry | Break out old floor tiles | m² | Floor area broken out |
| B03 | Demolition & masonry | Hack off old plaster | m² | Wall area hacked off |
| B04 | Demolition & masonry | Remove old doors and windows | No. | Number of pieces |
| B05 | Demolition & masonry | Half-brick walls | m² | Length × height minus openings |
| B06 | Demolition & masonry | Full-brick walls | m³ | Length × height × thickness minus openings |
| B07 | Demolition & masonry | Lintels over new openings | No. | Number of openings |
| C01 | Electrical | Feed cable from meter to distribution board | lm | Actual route length |
| C02 | Electrical | Distribution board with breakers | No. | Number of boards, each sized by number of circuits |
| C03 | Electrical | Lighting point (conduit, cable, box) | Point | Count from layout drawing |
| C04 | Electrical | Standard socket point | Point | Count from drawing |
| C05 | Electrical | Power socket point (AC, heater, oven) | Point | Number of heavy appliances |
| C06 | Electrical | Telephone or data point | Point | Count |
| C07 | Electrical | Satellite or TV point | Point | Count |
| C08 | Electrical | Doorbell or intercom point | Point | Count |
| C09 | Electrical | Spare empty conduits (data, cameras) | lm | Conduit length |
| C10 | Electrical | Earthing | Lump sum | Whole apartment |
| C11 | Electrical | Supply and fix switch and socket plates | No. | Number of plates from the layout drawing (one plate can serve several points) |
| C12 | Electrical | Downlights and spotlights | No. | Count from lighting plan |
| C13 | Electrical | Concealed LED lighting (strip or profile) | lm | Strip length |
| C14 | Electrical | Install chandeliers and special fittings | No. | Count |
| D01 | Plumbing | Bathroom water supply rough-in (hot and cold) | Point | Water points per bathroom (or lump sum per bathroom) |
| D02 | Plumbing | Bathroom drainage rough-in | Point | Drain points (or lump sum per bathroom) |
| D03 | Plumbing | Kitchen supply and drainage rough-in | Point | Count |
| D04 | Plumbing | Washing machine point (supply and drain) | Point | Count |
| D05 | Plumbing | Water heater point | Point | Number of heaters |
| D06 | Plumbing | Main supply line from meter or tank | lm | Route length |
| D07 | Plumbing | Main and branch valves | No. | Count |
| D08 | Plumbing | Floor drains | No. | Count |
| D09 | Plumbing | Connection to soil stack | No. | Number of connections |
| D10 | Plumbing | Pipe pressure test | Lump sum | Whole apartment |
| E01 | AC | Copper pipe rough-in | lm | Route length per unit (or point per unit by capacity) |
| E02 | AC | Condensate drain rough-in | lm | Route length to discharge point |
| E03 | AC | Opening and bracket for outdoor unit | No. | Number of units |
| E04 | AC | Install AC units | No. | Number of units (if not by supplier) |
| F01 | Waterproofing | Bathroom floor waterproofing turned up walls | m² | Floor area + perimeter × upstand height |
| F02 | Waterproofing | Kitchen floor waterproofing | m² | Floor area + upstand |
| F03 | Waterproofing | Balcony waterproofing | m² | Floor area + upstand |
| F04 | Waterproofing | Flood test | Lump sum | Per bathroom or waterproofed area |
| G01 | Plaster | Spatterdash (key coat) | m² | Same as plaster area |
| G02 | Plaster | Internal wall plaster with dots and screeds | m² | Room perimeter × height minus openings per deduction rule |
| G03 | Plaster | Ceiling plaster | m² | Room length × width |
| G04 | Plaster | Corner beads on external corners | lm | Length of corners |
| G05 | Plaster | Mesh at brick-to-concrete joints | lm | Length of joints |
| G06 | Plaster | Repair existing plaster (semi-finished units) | m² | Area needing repair |
| H01 | Floors & walls | Bathroom fill | m³ | Area × depth |
| H02 | Floors & walls | Levelling screed, if required | m² | Floor area |
| H03 | Floors & walls | Porcelain, ceramic or marble floors (inside the apartment) | m² | Net floor area per room |
| H04 | Floors & walls | Bathroom wall tiles | m² | Perimeter × tiling height minus door |
| H05 | Floors & walls | Kitchen wall tiles | m² | Wall length × tiling height |
| H06 | Floors & walls | Porcelain or marble skirting | lm | Perimeter of rooms with porcelain or marble floors, minus door widths |
| H07 | Floors & walls | Marble door thresholds | lm | Width of each door |
| H08 | Floors & walls | Marble window sills | lm | Width of each window |
| H09 | Floors & walls | Parquet or HDF with underlay | m² | Net floor area |
| H10 | Floors & walls | Parquet skirting | lm | Perimeter of rooms with parquet floors, minus door widths |
| H11 | Floors & walls | Balcony flooring | m² | Balcony area |
| I01 | Gypsum board | Suspended gypsum board ceiling | m² | Plan area of suspended ceiling |
| I02 | Gypsum board | Cove for concealed lighting | lm | Cove length |
| I03 | Gypsum board | Curtain pelmet | lm | Window or wall width |
| I04 | Gypsum board | Ready-made gypsum cornices | lm | Room perimeter |
| I05 | Gypsum board | Access and AC openings | No. | Count |
| I06 | Gypsum board | Gypsum board partitions or wall linings | m² | Length × height |
| J01 | Painting | Sealer | m² | Same as painted area (walls and ceilings) |
| J02 | Painting | Putty and sanding (number of coats) | m² | Same as painted area (walls and ceilings) |
| J03 | Painting | Wall paint (coats and brand) | m² | Perimeter × height minus openings per deduction rule, excluding tiled walls |
| J04 | Painting | Ceiling paint | m² | Painted ceiling area, including gypsum board surfaces |
| J05 | Painting | Special finishes or wallpaper | m² | Wall area specified |
| J06 | Painting | Metal painting (railings, iron windows and doors) | lm / m² | lm for railings, m² for iron windows and doors |
| K01 | Doors & windows | Apartment front door | No. | Count, with size |
| K02 | Doors & windows | Internal doors with frame and architrave | No. | Count, with size of each |
| K03 | Doors & windows | Handles, hinges and locks | Set | One set per door |
| K04 | Doors & windows | Aluminium windows with glazing (and shutters if required) | m² | Opening width × height per window |
| K05 | Doors & windows | Aluminium balcony doors | m² | Opening width × height |
| K06 | Doors & windows | Insect screens | m² | Sash area |
| K07 | Doors & windows | Balcony railing | lm | Railing length |
| L01 | Sanitaryware | WC (floor or wall-hung) with cistern | No. | Count |
| L02 | Sanitaryware | Washbasin with pedestal or bracket | No. | Count |
| L03 | Sanitaryware | Basin mixer | No. | Count |
| L04 | Sanitaryware | Shower or bath mixer (exposed or concealed) | No. | Count |
| L05 | Sanitaryware | Bathtub, shower tray or enclosure | No. | Count |
| L06 | Sanitaryware | Bidet spray (shattaf) | No. | Count |
| L07 | Sanitaryware | Water heater | No. | Count |
| L08 | Sanitaryware | Bathroom accessories (hooks, roll holder, mirror) | Set | One set per bathroom |
| L09 | Sanitaryware | Kitchen sink and mixer | No. | Count |
| M01 | Kitchen & joinery | Kitchen base units | lm | Run length |
| M02 | Kitchen & joinery | Kitchen wall units | lm | Run length |
| M03 | Kitchen & joinery | Worktop (marble, granite or quartz) | lm | Worktop length |
| M04 | Kitchen & joinery | Built-in wardrobes | m² | Front width × height |
| M05 | Kitchen & joinery | Install cooker hood | No. | Count |
| N01 | Handover | Testing of electrical and plumbing systems | Lump sum | Whole apartment |
| N02 | Handover | Rectification of handover snags | Lump sum | Per handover record; agree it is included in the item rates and has a deadline |