Bathroom Finishing Step by Step: Waterproofing to Tiles

By AFAQ Development team · Updated

Building site in Badr City: stone cladding going on under scaffolding on a residential building
From an AFAQ site in Badr City (a photo of the building site, not of a bathroom)

Bathroom finishing follows a fixed order: strip-out if needed, plumbing and electrical rough-in with a pressure test, waterproofing and a flood test, fill and screed, tiling with falls to the drain, a gypsum ceiling if wanted, then sanitaryware, mixers and accessories, and a final test. Any step done early gets broken out later, and the most expensive bathroom mistake is a leak that shows up in the neighbour’s ceiling after you have finished.

This guide is for owners of new apartments in Egypt, from social housing and Sakan Misr units to semi-finished flats in the new cities, and for anyone renovating an older bathroom. It includes the bathroom lines from AFAQ Development’s own BOQ template, so you know what should be written down before you sign.

In what order is a bathroom finished?

What gets buried is done and tested first; what can be scratched goes in last.

  1. Strip-out, if the bathroom is old or the layout is changing.
  2. Plumbing rough-in (hot, cold and drainage) and electrical rough-in (heater, lighting, extract fan).
  3. Pressure test before the pipes are closed up.
  4. Waterproofing on the floor, turned up the walls.
  5. Flood test before any tiling.
  6. Fill and screed, laid to fall towards the floor drain.
  7. Floor and wall tiles.
  8. Gypsum ceiling if required, with an access panel.
  9. Sanitaryware, mixers, water heater and accessories.
  10. Final test of every water and drain point.

For where the bathroom sits in the whole apartment sequence, see finishing stages in order.

Plumbing rough-in: what must be decided first?

Before any pipe is cut, the drawing should fix the position and height of every fixture (WC, basin, shower or bath, water heater, washing machine if it goes in the bathroom), plus the drain route and the floor drain position. A decision put off here comes back as broken tiles.

The key step is a pressure test before the pipes are closed up; it has its own line in our BOQ template (D10). Skip it, and the first leak appears under the tiles or in the flat below. The test pressure and duration go in the specification for the pipe type; ask for the result in writing. On the electrical side, plan a power point for the water heater (C05), the lighting, and an extract fan that actually vents outside. Sockets must be kept away from water spray, and their positions and types are for the engineer to set on the drawing.

Waterproofing: how is it done, and why is the flood test the key step?

The whole floor is waterproofed, turned up the walls and sealed around the drains, then flooded with water before any fill or tiling. The flood test is the only proof the waterproofing works; once the tiles are down, you will never see it again.

In the BOQ template, waterproofing (F01) is measured in square metres: floor area plus perimeter × upstand height; the flood test (F04) is a separate line. If a quotation does not list it, ask for it by name. Cementitious and bituminous systems are common in Egypt; the type, number of coats and upstand height are a specification for the engineer, not a brand choice, and they belong in the quotation. During the test the floor stays flooded for a period the engineer sets from the waterproofing specification, and someone checks the ceiling below before the water is drained. As a general reference, the US guide ASTM D5957 for flood testing horizontal waterproofing gives 24 hours minimum and 72 hours maximum (Intertek summary of the standard, 1998 edition as reapproved).

Ceramic or porcelain, and what matters in the laying?

Both work; the practical difference is on the floor, where you want a tile with slip resistance suited to wet use, keeping glossy tiles for the walls. Porcelain absorbs less water: under the US standard ANSI A137.1, a tile counts as porcelain if it absorbs 0.5% or less (ANSI blog). Ceramic is lighter and easier to cut, and the final choice rests on the size, grade and brand written into the quotation.

Laying matters more than the tile. The floor must fall to the drain so no water sits in corners; the bathroom floor level relative to the rest of the flat must be fixed before the door frame goes in; and grout lines should be even and fully filled. Tap every tile before handover: a hollow sound means poor bedding, and a hollow tile in a bathroom can crack and let water underneath.

Small bathroom: how do you make it work?

Save floor space first: a glass shower screen instead of a bath, a wall-hung WC or bracket basin, light colours and good lighting, decided before the rough-in, because they move the pipes. Large-format tiles mean fewer grout lines but need a very flat floor. Add a ceiling light, a light by the mirror, a working extract fan, and recessed shelves instead of projecting units. These are general tips; the final layout is drawn to your bathroom’s measurements.

Modern bathroom: what makes the difference?

Concealed mixers, a wall-hung WC, hidden lighting and large tiles with few joints, and the decision has to come before the rough-in. A concealed mixer body is built into the wall at rough-in; a wall-hung WC needs a frame and a concealed cistern. That is why our BOQ lines say “exposed or concealed” (L04) and “floor or wall-hung” (L01). The same applies to the whole flat; see apartment finishing with an itemised quote.

Social housing or Sakan Misr: what to check first?

Start with the specification annex in your contract: what exactly was the bathroom handed over with? Then test what is there before building on it: run the pipes and drains, look for damp on the ceiling and walls, and check the drain position and floor fall. Record any defect before you start; our semi-finished handover checklist walks through it. For any change to the bathroom position or drain route in a housing unit, check your contract and the responsible authority first, and let an engineer decide after a visit.

Bathroom items in the BOQ: what should be written?

Each bathroom item belongs on its own line, with its unit and material. This is an excerpt from AFAQ’s BOQ template, same codes, no prices:

Code Item Unit Write in
D01 Bathroom water supply rough-in (hot and cold) Point or lump sum per bathroom Pipe type, number of points
D02 Bathroom drainage rough-in Point or lump sum per bathroom Pipe type, drain route
D05 Water heater point Point Heater position
D07 Main and branch valves No. Number and position
D08 Floor drains No. Position on the drawing
D10 Pipe pressure test Lump sum Done before closing up
C05 Power socket point (including the heater) Point Number of heavy appliances
F01 Bathroom floor waterproofing turned up walls m² Type, brand, coats, upstand height
F04 Flood test Lump sum per bathroom Before fill and tiling
H01 Bathroom fill m³ Fill material
H03 Porcelain, ceramic or marble floors (including the bathroom floor) m² Brand, size, grade
H04 Bathroom wall tiles m² Brand, size, grade, tiling height
L01 WC (floor or wall-hung) with cistern No. Type, brand
L02 Washbasin with pedestal or bracket No. Type, brand
L03 Basin mixer No. Brand
L04 Shower or bath mixer (exposed or concealed) No. Exposed or concealed, brand
L05 Bath, shower tray or enclosure No. Type, size
L06 Bidet spray (shattaf) No. Brand
L07 Water heater No. Type, capacity
L08 Bathroom accessories Set Pieces included

On every line, write the brand, size and grade, not just “tiles”. Commonly forgotten: the pressure test, the flood test, accessories, and an access panel in a gypsum ceiling. The full template is free to download: apartment finishing BOQ (Excel and PDF).

How much does bathroom finishing cost?

It depends on the bathroom’s size, whether it is new or being stripped out, the waterproofing, the tiles and their size, and above all the sanitaryware and mixers. Two bathrooms of the same size can cost very different amounts. AFAQ does not quote a flat price per bathroom or per metre: the price is set after a site visit and sent as an itemised quotation, turnkey with materials or labour-only, as you choose.

How do you check a finished bathroom?

Test it working, not just by eye, and record every snag before you sign.

  1. Open every hot and cold point; check pressure and look for drips at joints.
  2. Run the basin, shower and WC together; water should drain fast with no smell.
  3. Pour water in several corners and watch it run to the drain.
  4. Tap the tiles and note any hollow sound.
  5. Check the grout is full and even, and the joints around fixtures are sealed.
  6. Push the WC, basin and mixers; nothing should move.
  7. Run the heater, fan and lights.
  8. After a few days of use, check the ceiling of the flat below for damp.

Finishing a bathroom with AFAQ

AFAQ Development carries out bathroom plumbing, electrical rough-in and waterproofing as part of apartment finishing, with every item and material written into the quotation before work starts and the work following a fixed sequence under an engineer’s supervision. The work carries a one-year warranty, detailed in the contract.

Send us on WhatsApp photos of the bathroom as it is now and its size, with the apartment’s size and the work you need. Or download the BOQ template, see apartment finishing, or get in touch.

Frequently asked questions

Does waterproofing go before or after the tiles?

Before. The floor is waterproofed and turned up the walls after the plumbing rough-in and pressure test, then flood-tested, and only after the test passes come the fill and the tiles. Tiles themselves do not waterproof a bathroom.

How long does a flood test take?

There is no single duration: the engineer sets it from the waterproofing type and the manufacturer's specification. As a general reference, the US guide ASTM D5957 for flood testing horizontal waterproofing gives a minimum of 24 hours and a maximum of 72. What matters is that the water stays in until someone has checked the ceiling of the flat below for damp, and that the result is recorded.

Which waterproofing is best for a bathroom?

No single type suits every bathroom. Cementitious and bituminous systems are both common in Egypt; the choice depends on the floor's condition and the engineer's specification. The type, brand and number of coats should be written into the quotation.

Can I move the bathroom to another part of the apartment?

That is an engineer's decision after a site visit, because it depends on the drain route, the soil stack, pipe falls and the ceiling below. In a compound or a state housing project, check your contract and the responsible authority before any change.

How long does bathroom finishing take?

It depends on whether the bathroom is new or being stripped out, its size, delivery times for tiles and sanitaryware, and the time waterproofing and tests need. A written schedule by stage is the reference; do not cut the flood test short to save a couple of days.